Priority Programmes and Projects for Roads and Works (2012 - 2015)

  Total Target / Cost 
Programme / Project
& Budget No. and Policy Initiative
Objective Strategies Output Performance Indicator 2012 - 2013 2013 - 2014 2014 - 2015
Major Projects
Road Rehabilitation (Parochial Act) To improve and upgrade parochial roads throughout the parish Survey and prepare estimates.
Secure funding from central government and other funding agencies
Improved road network To rehabilitate 16km of parochial road throughout the parish Rehabilitate 6km of road in the parish
(Cost $60 mil)
Rehabilitate 5km of Road in the parish
(Cost $60 mil)
Rehabilitate 5km of road in the parish
(Cost $72 mil)
Road Maintenance To minimise flooding and protect existing road network Clean drains. Clear outlets.
Debush road bank and cut overhangs. Patching. Repair kerb and channel.
Clean drains. 
Repaired roads. 
Ease in traffic flow.
 
To clean 20km of critical drains in the parish.
To debush 12km of road embankment throughout the parish
To clean 6km of drain
(cost $2.4mil)
To debush 4km of road embankment
(cost $800,000)
To clean 6km of drain
(cost $2.4mil)
To debush 4km of road embankment
(cost $960,000)
Too clean 6km of drain
(cost $2.4mil)
To debush 4km of road embankment
(cost $1.2mil)